Electronic Gas Lighters
Product Code (ASICC) | 77134 The following BIS Standards may be referred: IS 11514:1985 Piezo electric ceramic cartridge for impact type gas lighters. IS 11519:1985 |
Quality and Standards | Piezo electric ceramic cartridge for squeeze type of gas lighters. IS 11013:1984 Piezo electric ceramic elements (impact type and squeeze type). |
Production Capacity | Qty.: 30,000 Nos. (per annum) Value: Rs 15.00 lakhs |
Uploaded on | March 2007 |
Introduction
The electronic gas lighter uses a piezo-electric crystal. This crystal has a property to generate voltage when it is mechanically deformed. It generates high voltage across a spark gap which when in proximity to a gas would ignite it. Gas lighters are being used by cooking gas users. It is durable due to its performance and economical as compared to the mechanical and electrical lighters. It does not require battery for its operation. It is safer, economical, reliable and quick in action. It requires virtually no maintenance.
Market Potential
The demand of any type of gas lighter is directly related to the use of domestic gas connections by various household in the country. However, users go in for various types of gas lighting devices i.e. matches, electrical or electronic gas lighter. The preference to use electronic gas lighters is quite high because of its inherent advantages stated above. Even existing gas users have been increasingly switching over to electronic gas lighters. At present, there are about 50 small scale units engaged in the manufacture of electronic gas lighter with an average capacity of 30,000 to 50,000 per annum. The cost of gas lighter is very well within the reach of users and therefore demand is increasing day by day.
Basis and Presumptions
- The basis for calculation of production capacity has been taken on single shift basis on 75% efficiency.
- The maximum capacity utilization on single shift basis for 300 days a year. During first year and 2nd year of operation the capacity utilisation is 60% and 80% respectively. The unit is expected to achieve full capacity utilisation from the 3rd year onwards.
- The salaries and wages, cost of raw-materials, utilities, rents etc. are based on the prevailing rates in and around Solan (H.P.). These cost factors are likely to vary with time and location.
- Interest on term loan and working capital loan has been taken at the rate of 16% on an average, prevailing. This rate may vary depending upon the policy of the Financial Institutions/Agencies from time to time.
- The cost of machinery and equipments refer to a particular make/model and the prices are approximate.
- The break-even point percentage indicated is of full capacity utilization.
- The project preparation cost etc. whenever required could be considered under pre-operative expenses.
- The essential production machinery and test equipment required for the project have been indicated. The unit may also utilize common test facilities available at Electronics Test and Development Centres (ETDCs) and Electronic Regional Test Laboratories (ERTLs) set up by the State Governments and STQC Directorate of the Department of Information Technology, Ministry of Communication and Information Technology, to manufacture products conforming to Bureau of Indian Standards.
Implementation Schedule
The major activities in the implementation of the project has been listed and the average time for implementation of the project is estimated at 12 months
Name of Activity |
Period in Months (Estimated) |
Preparation of project report | 1 |
Registration and other formalities | 1 |
Sanction of loan by financial institutions | 3 |
Plant and Machinery | |
(i) Placement of orders | 1 |
(ii) Procurement | 2 |
(iii) Power connection/ Electrification | 2 |
(iv) Installation/Erection of machinery/Test Equipment | 2 |
Procurement of Raw materials | 2 |
Recruitment of Technical Personnel etc. | 2 |
Trial Production | 11 |
Commercial Production | 12 |
Notes
- Many of the above activities shall be initiated concurrently.
- Procurement of raw materials commences from the 8th month onwards.
- When imported plant and machinery are required the implementation period of project may vary from 12 months to 15 months.
Technical Aspects
Process of Manufacture Sheet metal components/parts are being manufactured with the help of hacks, saw machines, hand press, drilling machine, spot welding machine, etc. Moulded components are made on injection moulding machine. The metal turned parts are made on lathe machine. Assembly, on piezo electric ceramic cartridge along with sheet metal components/parts and moulded parts are carried out and fitted in M.S. tubing/cases. The complete assembled unit is tested for life cycle ignition before it is sent for packing and despatch.
Quality Control and Standards
There is no BIS standard for this product, however the following Specifications may be referred for quality:
IS 11514:1985 Piezo electric ceramic catridge for impact type of Gas Lighters.
IS 11519:1985 Piezo electric ceramic catridge for squeeze type of Gas Lighters.
IS 11013:1985 Piezo electric ceramic elements (Impact type and squeeze type) for Gas Lighters.
It is envisaged that the gas lighter will be able to perform the following operations
- To generate voltage above 10 KV.
- Period of spark generation should not be less than 10 milli second.
- The gas lighters must be able to operate more than 30,000 times.
Production Capacity
Quantity (per annum) | Value (Rs.) |
30,000 Nos. | 15.00 lakhs |
Motive Power | 10 KVA. |
Pollution Control
The Govt. accords utmost importance to control environmental pollution. The small-scale entrepreneurs should have an environmental friendly attitude and adopt pollution control measures by process modification and technology substitution.
India having acceded to the Montreal Protocol in Sept. 1992, the production and use of Ozone Depleting Substances (ODS) like Chlorofluoro Carbon (CFC), Carbon Tetrachloride, Halons and Methyl Chloroform etc. need to be phased out immediately with alternative chemicals/solvents. A notification for detailed Rules to regulate ODS phase out under the Environment Protection Act, 1986 have been put in place with effect from 19th July 2000.
The following steps are suggested which may help to control pollution in electronics industry wherever applicable
- In electronic industry fumes and gases are released during hand soldering/wave soldering/Dip soldering, which are harmful to people as well as environment and the end products. Alternate technologies may be used to phase out the existing polluting technologies. Numerous new fluxes have been developed containing 2-10% solids as opposed to the traditional 15-35% solids.
- Electronic industry uses CFC, Carbon Tetrachloride and Methyl Chloroform for cleaning of printed circuit boards after assembly to remove flux residues left after soldering, and various kinds of foams for packaging.
Many alternative solvents could replace CFC-113 and Methyl Chloroform in electronics cleaning. Other Chlorinated solvents such as Trichloroethylene, Perchloroethylene and Methylene Chloride have been used as effective cleaners in electronics industry for many years. Other organic solvents such as Ketones and Alcohols are effective in removing both solder fluxes and many polar contaminants.
Energy Conservation
With the growing energy needs and shortage coupled with rising energy cost, a greater thrust in energy efficiency in industrial sector has been given by the Govt. of India since 1980s. The Energy Conservation Act, 2001 has been enacted on 18th August'2001, which provides for efficient use of energy, its conservation and capacity building of Bureau of Energy Efficiency created under the Act. The following steps may help for conservation of electrical energy
- Adoption of energy conserving technologies, production aids and testing facilities.
- Efficient management of process/manufacturing machineries and systems, QC and testing equipments for yielding maximum Energy Conservation.
- Optimum use of electrical energy for heating during soldering process can be obtained by using efficient temperature controlledsoldering and desoldering stations.
- Periodical maintenance of motors, compressors etc.
- Use of power factor correction capacitors. Proper selection and layout of lighting system; timely switching on-off of the lights; use of compact fluorescent lamps wherever possible etc.
Financial Aspects
Land and building
The building is considered as rental with a rent of Rs. 2500 per month having covered area of 150 sq. mtrs.
Description |
(Nos.) |
Value (Rs.) |
Precision type bench lathe (4 1/2" feet bed with 2 HP motor) | 2 | 15,00,00 |
Tube extrusion unit complete with reduction gear, size 6" dia with 10 H.P. motor.Fly press (No.31) | 1 | 2,00,000 |
Bench Drilling Machine (1/2") | 4 | 8,00,000 |
Bench Grinder | 1 | 20,000 |
Shearing machine (10" × 10" SWG) | 1 | 25,000 |
Injection Moulding machine 15 Gm | 1 | 90,000 |
Test Bench with Jigs filted (Motorised) | 1 | 4,00,000 |
Spot welding machine | 2 | 3,50,000 |
Cost of dies/mould/Tools and Fixtures | 1 | 6,00,000 |
Total | 90,000 | |
Add, 10% of the total cost of machinery, equipments towards electrification charges | 9,000 | |
Total | 99,000 | |
Cost of office equipment/furniture | 20,000 | |
Pre-operative Expenses | 10,000 | |
Total Fixed Capital | 39,000 | |
Total | 1,29,000 |
B. Working Capital (per month)
(i) Staff and Labour
Designation |
No. |
Salary (Rs.) |
Total (Rs.) |
Staff | |||
Manager | 2 | 12,000 | |
Sales Asstt. | 1 | 5,000 | |
Clerks/Typists | 2 | 6,000 | |
Peon/Watchman | 3 | 10,000 | |
Total | |||
Labour | |||
Skilled workers | 3 | 2000 | 6000 |
Semi-skilled Worker | 2 | 1500 | 3000 |
Total | 9,000 | ||
Total (a+b) | 20,000 | ||
Add 15% perquisites towards, PF, Bonus etc. | 3000 | ||
Total | 23,000 |
(ii) Raw Material Requirement (for 2500 Gas Lighters) (per month)
Particulars |
Qty. |
Peizo electric ceramic cartridge/slug | 2500 Nos. |
Copper Contacts | 2500 sets. |
M.S. Tubing | 500 Mtrs. |
Spring | 2500 Nos. |
Plastic powder/granules | 15 Kgs |
M.S. Strip | 50 Kgs. |
Hardware | 2500 sets |
Packing materials | 2500 sets |
The average cost of raw material per set works out to be Rs. 27 per set.
Total Cost of Raw Material (per month) for 2500 Nos.
Gas Lighters | 67,500 |
(iii) Utilities
(Rs.) |
|
Power | 3,000 |
Water | 300 |
Total | 3,300 |
(iv) Other Contingent Expenses (per annum)
Particulars |
Value (Rs.) |
Rent | 2,500 |
Postage and Stationery | 500 |
Consumable | 500 |
Repairs and maintenance | 1,000 |
Conveyance and transport | 3,000 |
Advertisement and Publicity | 2,000 |
Insurance | 500 |
Miscellaneous expenses | 1,000 |
Total | 11,000 |
( v) Total Recurring Expenditure (per month) (i+ii+iii+iv) | 10,4800 |
C. Total Capital Investment
Fixed capital | 1,29,000 |
Working capital (for 3 months basis) | 3,14,400 |
Total | 4,43,400 |
Financial Analysis
Cost of Production (per annum) |
(Rs) |
Working capital | 12,57,600 |
Depreciation on Machinery and equipment @ 10% | 9,000 |
Depreciation on office equipment/ furniture @ 20% | 4,000 |
Interest on total capital Investment @ 16% |
70,944 |
Total | 13,41,544 |
Say | 13,41,500 |
Turnover (per annum)
Item |
Qty. |
Rate (Rs.) |
Total (Rs.) |
Electronic Gas Lighter | 30,000 | 50 | 15,00,000 |
Profit | 1,58, 500 |
Profit Ratio | 10.57% |
Rate of Return | 35.75% |
Break-even Point
Fixed Cost |
(Rs) |
Annual Rent | 30,000 |
Depreciation | 13,000 |
Interest | 70,944 |
40% of salary and wages | 11,04,00 |
Insurance/Taxes | 6,000 |
40% of other contingent expenses and utilities (excluding rent and insurance) | 54,240 |
Total | 28,45,84 |
Say | 28,45,00 |
B.E.P | Fixed cost × 100 Fixed cost + profit
|
|
64.22% |
Additional Information
- The Project Profile may be modified/tailored to suit the individual entrepreneurship qualities/capacity, production programme and also to suit the locational characteristics, wherever applicable.
- The Electronics Technology is undergoing rapid strides of change and there is need for regular monitoring of the national and international technology scenario. The unit may, therefore, keep abreast with the new technologies in order to keep them in pace with thedevelopments for global competition.
- Quality today is not only confined to the product or service alone. It also extends to the process and environment in which they are generated. The ISO 9000 defines standards for Quality Management Systems and ISO 14001 defines standards for Environmental Management System for acceptability at international level. The unit may therefore adopt these standards for global competition.
- The margin money recommended is 25% of the working capital requirement at an average. However, the percentage of margin money may vary as per bank's discretion.
Addresses of Machinery/Equipment and Raw Material Suppliers
Machinery/Equipment
- M/s. Perfect Machine Tools Co.
Sir P. M. Road,
Mumbai-400007. - M/s. Batliboi and Co.
G.T. Road,
Delhi-110006. - M/s. Jeet Machine Tools,
Corporation
Shardanand Marg,
Delhi-110006.
Raw Material
- M/s. Calico Chemical and
Plastic Fibres Division
Anik Chambers,
Mumbai-400074.
(for Plastic Materials) - M/s. Central Electronics Ltd.
Industrial Area, Sahibabad,
Distt. Ghaziabad (U.P.)
(for Piezo Ceramics) - M/s. Brisk Electro Sales (P) Ltd.
394-A, Lamington Road,
Lamington Chambers,
Mumbai-400004.
(for Piezo Ceramics). - M/s Keltron Crystals Ltd.
Keltron Nagar, Mangatparamba,
P.O. Kalliasseri,
Cannanore-670562.
(for Piezo Crystals)